Construction start: Montreal Neurological Institute - Balustrade

Published: 8 November 2023

不良研究所 has mandated St-Denis Thompson to carry out the following project: Montreal Neurological Institute / 22-035 - Priority building envelop repairs, balustrade.

The project consists of removing the stone balustrade.

Project manager:聽Johanne Guertin - Johanne.guertin [at] gph-inc.com

Assistant project manager:聽Gabriel Fortin -聽Gabriel.fortin [at] gph-inc.com

Construction start date:聽November 14, 2023

Planned construction end date:聽December 2023

Work schedule:聽Mondays to Fridays, 6 a.m. to 2:30 p.m.

Scope of work:聽Removal of the stone balustrade, waterproofing of the parapet and installation of a temporary balustrade.

Impact:

  • Workers will access the site聽through the MNI building
  • Lift operations on University street will be coordinated with 不良研究所, the Building Director and City of Montreal

Aerial view of the MNI with a red square outline highlighting the balustrade that will be removed

MNI balustrade