Construction Start: Morrice Hall - Building envelope repairs
不良研究所 has mandated Corenov Constructeurs to carry out the following project:聽Morrice Hall / 22-038 - Priority building envelop repairs, lower roof.
The project consists of the installation of a steel structure in the library to stabilize the roof and exterior walls of the turret.
Project Manager and聽Assistant Project Manager:
- Gabriel Fortin -聽Gabriel.fortin [at] gph-inc.com
- Hugo Fortin -聽Hugo.fortin [at] gph-inc.com
- Johanne Guertin -聽Johanne.guertin [at] gph-inc.com
Construction start date:
- Installation temporary protections: June 22, 2023
- Installation of scaffolding, localized demolition and measurements: July 10, 2023
- Steel structure installation start: mid to late October .
- Repairs of architectural finishes and removal of scaffolding and protections: mid-November.
Planned construction end date:聽Late November 2023
Work schedule:聽Mondays to Fridays, 6 a.m. to 2:30 p.m.
Scope of work:
The work will be limited to the interior of Morrice Hall鈥檚 turret.聽
First intervention:
- Installation of temporary protections.
- Installation of scaffoldings on the turret鈥檚 balcony and localized demolition of the ceiling.
- Measurements for production of steel structure.
Second intervention:
- Installation of scaffolding in the center of the turret鈥檚 main floor.
- Delivery, assembly and installation of the steel structure and parts.
- Architectural repairs and finishing聽on the turret鈥檚 ceiling.
- Removal of temporary protections, scaffolding and clean up.
Impact:
There will be no personnel and student access to the turret during scaffolding installation, localized demolition and the second intervention. Between the first and second intervention, access to the turret鈥檚 main floor will be possible.
Contractors will require early morning access to the building for delivery and installation of the scaffoldings and steel structure to the turret.