Construction Starts: Currie Gym - Replacement of the Multistack Chiller

Please be advised that 不良研究所 has mandated Plomberie Charbonneau to carry out the following project:聽23-012 - Currie Gym - Replacement of the multistack chiller
顿别蝉肠谤颈辫迟颈辞苍:听Installation of a new main chiller and its integration into the building control system.
Construction start date:聽February 17, 2025
Planned construction end date:聽May 30, 2025
Work schedule:聽Monday to Friday, 6:30 a.m. to 3 p.m. Works outside of building hours will be coordinated in advance.
Project Manager: mona.modaressi [at] mcgill.ca (Mona Modaressi)
Assistant Project Manager: thomas.perreault [at] mcgill.ca (Thomas Perreault)
Contact for building users: angelo.battista [at] mcgill.ca (Angelo Battista)
--------------------------------------------------------------------------------------------------------
Scope of work:
The purpose of this project is to replace the main chiller that has reached the end of its useful life.
- Removal and disposal of the existing main chiller
- Procurement and installation of a new main chiller
- Integration of the new chiller system with the building's control system
- Performance testing and verification of the new chiller system to ensure it meets the specified requirements
Impact & mitigation:
- List of short-term impacts:
- Partial or total closure of the fitness centre will be necessary for 1 or 2 days. Building users will be informed in advance.
- Service shutdowns:
- Some work may require service shutdowns (e.g., electrical, ventilation). Building users will be informed in advance of these shutdowns.